Steps of PPAP during new development | Production part approval process

Purpose of PPAP:

The purpose of PPAP is to provide evidence that all customer engineering design records & specifications requirements are properly understood by the organization.

PPAP full form is the Production Part Approval Process. The manufacturing process has the potential to produce the product consistently meeting these requirements during an actual production run at the quoted production rate.

Scope:

The procedure applies to all products manufactured in the organization and by its suppliers.  Production part review and approval are required for each part before the first quantity shipment in the situations described later.

Responsibility:

The primary responsibility of PPAP is with the NPD Head, with the support of other department heads.

What is a Significant Production Run?

The significant production run shall be from 1 hour to 8 hours of production. Also quantity produced can be a minimum of 300 consecutive parts or as specified by the customer. The significant production run shall be done at the production site with production tools, production materials, production process & production operators.   

When is PPAP submission required?

Production Part Approval Process (PPAP) shall be required for each part before the first quantity shipment in the situations mentioned below:

  • A new part.
  • Correction of an abnormality on a previously submitted part.
  • Engineering change to design records, specifications or materials for production product/part numbers.
  • RM or BOP supplier change
  • Part production at a new location
  • The tooling has not been running for one year

PPAP Documents List:

  1. Design Record/ Drawing
  2. Authorized Engineering Change Documents
  3. Customer Engineering Approval
  4. Design Failure Mode and Effect Analysis
  5. Process Flow Diagram
  6. Process Failure Mode and Effect Analysis
  7. Control Plan
  8. MSA Study
  9. Initial Process Study
  10. Dimension Results/Inspection Records
  11. Performance Test records
  12. Material test records
  13. Qualified Laboratory Documentations
  14. Appearance Approval Report
  15. Samples Production Parts
  16. Master Samples
  17. Checking Aids
  18. Customer Specific Requirements
  19. Parts Submission Warrant

19 elements of PPAP:

1. Design Records :

The Organization shall have the design record of the product. A printed copy of the latest drawing needs to be provided. Drawing is provided by the customer when responsible for design.

2. Authorized Engineering Change Documents:

A document that shows the detailed description of the change that was not included in the Drawing. But it is done in the product or any child part.

3. Customer Engineering Approval:

The organization shall have evidence of customer engineering approval when any revision is made internally or by the customer.

4. DFMEA :

A copy of the Design Failure Mode and Effect Analysis (DFMEA), if the supplier is responsible for the design. If the customer is responsible for designing the list of all critical or high-impact product characteristics should be shared with the supplier, so they can be addressed on the PFMEA and Control Plan.  

5. PROCESS FLOW DIAGRAM (PFD) :

A copy of the Process Flow, indicating all steps and sequences in the production process, including incoming components. The organization shall have a process flow diagram in a specified format that clearly describes the production process steps & sequence.  

6. PFMEA

A copy of the Process Failure Mode and Effect Analysis (PFMEA). The PFMEA follows the Process Flow steps and indicates “what could go wrong” during the production and assembly of each component. It is a tool to identify and address failure modes in products and processes. 

7. Control Plan ( CP) :

A copy of the Control Plan. The Control Plan follows the PFMEA steps and provides more details on how the “potential issues” are checked in the incoming quality, assembly process or during inspections of finished products.  A control plan is the documented description of the system and processes required for controlling the manufacturing of the product. It is also a live document.

8. Measurement System Analysis Studies (MSA):

MSA usually contains the Gage R & R for the critical or high-impact characteristics and a confirmation that the instruments used to measure these characteristics are calibrated. Also the appraiser (inspector) is skilled enough to inspect the parts. Measurement data monitors nearly every process. As data quality improves, decision quality improves.  

9. Dimensional Results :

A list of every dimension noted on the ballooning drawing. This list shows the product characteristics, specifications, measurement results and the assessment showing if this dimension is “OK” or “Not OK”. Usually, a minimum of 5 pieces is reported per product/process combination.  

10. Records of Material / Performance Tests :

A summary of every test performed on the part. This summary lists each test, when it was performed, the specification, results and the assessment pass/fail.  

11. Material Test Report :

The report for material samples is initially inspected. It can be provided by the RM supplier or we can test the raw material from a third-party testing laboratory. 

12. Initial Process Studies (SPC):

Includes all Statistical Process Control charts affecting the most critical characteristics. The intent of SPC is to demonstrate that critical processes have stable variability and that are running near the intended nominal value & the process is capable/under control.  

13. Qualified Laboratory Documentation :

Copy of all laboratory certifications of the laboratories that performed the tests.  

14. Appearance Approval Report : 

A copy of the AAI (Appearance Approval Inspection) form was signed by the customer. Applicable for components affecting appearance only. The appearance includes information about the color, textures etc.

15. Sample Production Parts :

A sample from the same lot of initial production run. The PPAP package usually shows a picture of the sample and where it is kept (customer or supplier).  

16. Master Sample :

A sample signed off by the customer and supplier usually is used to train operators on subjective inspections such as visual.  

17. Checking Aids :

When there are special tools and instruments for checking parts, this section shows a picture of the tool and calibration records, including the dimensional report of the tool.  

18. Customer-Specific Requirements :

Each customer may have specific requirements (CSR) to be included in the PPAP package. It is a good practice to ask the customer for PPAP expectations before even quoting for a job  

19. Part Submission Warrant (PSW) :

This is the form that summarizes the whole PPAP package. This form shows the reason for submission (design change, annual re-validation etc.) and the level of documents submitted to the customer. There is a section that asks for “results meeting all drawing and specification requirements: yes/no” which refers to the whole package. If there are any deviations, the supplier should note on the warrant or inform that PPAP can not be submitted.  

Submission Level during PPAP:

Below are the 5 Levels of PPAP:

  • Level 1: Part Submission Warrant only.
  • Level 2: Warrant with product samples and limited supporting data submitted to the customer.
  • Level 3: Warrant with product samples and complete supporting data submitted to the customer.
  • Level 4: Warrant and other requirements as defined by the customer.
  • Level 5: Warrant with product samples and complete supporting data reviewed at the manufacturing site.

PPAP,PSW


Note: By default, Submission Level 3 is to be submitted to the customer.

The level of PPAP submission required for a specific product is typically determined by the customer, who will specify the level in their purchase order or supplier requirements document.

Some common errors that can occur during a PPAP submission include incomplete documentation, incorrect data, and lack of compliance with specific requirements. To avoid these errors, suppliers should carefully review all requirements and documentation before submitting their PPAP and work closely with the customer to address any issues that arise.

Benefits of PPAP submission:

  • It identifies issues during the new development stage
  • It helps in managing the supplier change
  • PPAP submission ensures all required documents are prepared.
  • Ensure that the supplier is capable of meeting mass production
  • It prevents the supply of unapproved and non-conforming parts
  • It improves the product quality and ensures fulfillment of customer requirements & specifications.
  • It reduces the cost of poor quality COPQ.
  • Improve customer satisfaction

PPAP is a critical element of regulatory compliance and certification requirements in the automotive industry. PPAP is often required by industry standards such as IATF 16949 and is also often requested by customers as part of their supplier requirements.


FAQ related to PPAP | PPAP Questions:

Test your knowledge by answering the questions below in the comment section.

  • Que. 1 What does PPAP stand for?
  • Que. 2 What are the five levels of PPAP submission?
  • Que. 3 What are the key elements of a PPAP document?
  • Que. 4 Why is PPAP important in the automotive industry?
  • Que. 5 How is PPAP related to quality control and assurance?
  • Que. 6 What is the difference between a PPAP and an APQP process?
  • Que. 7 Who is responsible for conducting a PPAP submission and when should it be performed?
  • Que. 8 How do you determine which level of PPAP submission is required for a specific product?
  • Que. 9 What are some common errors that can occur during a PPAP submission and how can they be avoided?
  • Que. 10 How does PPAP relate to regulatory compliance and certification requirements in the automotive industry?
  • Que. 11 What is its purpose of PPAP?
  • Que. 12 What is included in each level of PPAP?

Note: Write your answer to the above question in the message by the question number

The answer to all the above questions is included in the blog post. Read the topic and find the answer.

You may like to read about other Core Tools:

  1. Advanced Product Quality Planning (APQP)
  2. Statistical Process Control (SPC)
  3. Measurement System Analysis (MSA)
  4. Failure Mode Effect Analysis (FMEA)
  5. Control Plan (CP)

4 thoughts on “Steps of PPAP during new development | Production part approval process”

  1. Found informative. Thanks for providing knowledge and sharing. Very helpfull in making career in quality management system.

    Reply

Leave a Comment